Solar for Mandi Gobindgarh steel plants and rolling mills.

Steel uses power around the clock; solar produces only in daylight. For induction furnaces, re-rolling mills and foundries in Mandi Gobindgarh, the useful question is not how many megawatts to buy but how many solar units your production can absorb. This guide covers the data to collect, the Punjab rules that shape the answer and the contract terms that protect a steel plant.

BPD Developer · Ludhiana & ChandigarhPublished 19 October 20268 min read

Key points

  • Size solar from interval demand across a normal day, a low-production day and a shutdown day, not from sanctioned load or installed furnace capacity.
  • A solar-only PPA supplies daytime energy. It does not provide round-the-clock power or backup during a grid outage.
  • In Punjab, a green energy open access consumer cannot change its open access quantum for at least twelve consecutive 15-minute blocks, and total drawal from open access and the licensee is capped at the sanctioned contract demand.
  • Banking can absorb part of the surplus from shutdowns, up to 30% of monthly consumption from the licensee, but banked energy cannot be drawn in the peak season or peak hours.

Why steel plants are looking at solar

Melting, re-rolling, forging and casting are energy-intensive operations. Daytime solar can displace part of the grid energy they use. How large a part depends on how much of the plant’s load runs in daylight, and on whether the solar supply can follow production when it changes.

BPD Developer power-supply focus is steel plants, rolling mills, induction furnaces, foundries and forging units, with priority for sanctioned loads above 5 MW. That is our commercial focus, not a legal minimum for open access. Our team works from Ludhiana.

Start with the production pattern

A steel plant’s power decision starts with production: melting cycles, rolling shifts, shutdowns and the load that remains when solar is available. Each operation needs different data.

OperationWhat to record
Induction furnace and meltingInterval demand through complete heat cycles, not just installed furnace capacity. Include starts, holding periods, production interruptions and the shared auxiliary load.
Rolling and re-rollingThe rolling schedule, idle periods and planned maintenance. Separate production demand from the factory’s continuous electrical base load.
Foundry and forgingBatch melting, heat treatment, presses and auxiliaries. If shifts vary by product or season, include representative days for each pattern.

Compare at least a normal production day, a low-production day and a shutdown day. If a furnace is stopped while the rolling mill runs, the electricity profile differs from a day when both operate together, and the solar allocation has to work on both.

Matching solar to the furnace and the mill

Solar output follows the sun: it rises through the morning, peaks around midday and falls away by evening. The share of solar a plant can use directly is the overlap between that curve and the plant’s demand in each 15-minute block.

For scale, the planning range we use for Punjab rooftop systems is about 1,500–1,650 kWh per kWp per year, so each megawatt-peak of solar produces roughly 1.5 to 1.65 million units a year. The annual figure is the easy part. What decides the useful size is how those units arrive hour by hour against the furnace and mill schedule.

  • Sanctioned load is one input, not the answer. A 6 MW sanctioned load does not mean a 6 MW solar plant. Useful capacity depends on interval demand, generation, existing solar, approved connection limits and settlement conditions.
  • Count existing solar first. Rooftop panels on the rolling mill shed, or any captive supply, already cover part of the daytime load. Allocating the same load to two sources overstates the benefit.
  • Use the full year. Twelve months of bills show seasonal output, holidays and the months when furnaces run less. A single peak month overstates what solar can replace.

Punjab rules that shape a steel plant’s solar supply

Steel plants comfortably clear Punjab’s eligibility threshold for green energy open access: a sanctioned contract demand of 100 kVA or more (PSERC 11th Amendment, 2023). The rules that matter more are about how power is scheduled and settled.

Scheduling in 15-minute blocks

A green energy open access consumer cannot change the quantum of power taken through open access for at least twelve consecutive 15-minute blocks in a day (PSERC 10th Amendment, Regulation 28(3)(A)). For a furnace whose demand swings within a heat, the open access schedule has to be set at a level the plant reliably uses through each three-hour window.

Drawal is capped at contract demand

Total drawal from open access and from the distribution licensee must stay within the sanctioned contract demand. In each block, admissible drawal from the licensee is the sanctioned contract demand minus the scheduled open access entitlement. Variations are dealt with under Regulation 31, which provides for demand surcharge on a daily basis when recorded drawal exceeds the admissible drawal, and treats drawal below the open access schedule as under-drawal.

Banking for shutdown days

Banking is allowed throughout the year on charges levied in kind, up to 30% of total monthly consumption from the licensee (10th Amendment). Banked energy cannot be drawn in the peak season or peak hours approved in the tariff order (12th Amendment, 2025), and it lapses if unused at the end of the 1 June to 31 May settlement period (13th Amendment, 2026). Banking softens a weekly holiday; it does not make a long maintenance shutdown free.

Wheeling

Renewable power wheeled within Punjab pays transmission and wheeling charges at 2% of the energy injected, irrespective of distance (12th Amendment). The landed cost guide shows what that does per unit.

Group captive or third-party PPA for a steel plant

DecisionGroup captive PPAThird-party open access PPA
Consumer participationConsumer ownership and captive compliance must be structured (at least 26% ownership and 51% consumption collectively)Review the offered non-captive supply arrangement and approvals
Commercial comparisonInclude equity, security, applicable charges and compliance obligationsInclude applicable surcharges, network costs and payment security
Energy commitmentTest contracted allocation against consumption and captive obligationsTest contracted allocation, minimum offtake and settlement terms
Supply balanceResidual utility supply and any separate storage or firmingResidual utility supply and any separate storage or firming

For a steel group with several companies, the 2026 version of Rule 3 treats a captive user together with its holding company and subsidiaries as one captive user, and lets the group allocate its eligible captive consumption among those entities. Each factory location still needs its own meter and utility schedule; an aggregate group load does not replace the connection-by-connection review.

See how group captive works in Punjab for the ownership and verification rules.

What to settle in the term sheet

Ask for a unit-by-unit energy reconciliation: generation at the agreed billing point, applicable losses, delivered allocation, energy actually used and remaining utility purchase. Show capacity-based charges and retained demand obligations alongside it. Then close four groups of terms:

  • Power and metering: project, delivery and billing points; settlement data; allocation; treatment of short supply.
  • Ownership and security: for a captive route, consumer equity and compliance responsibilities; separately, payment security and credit review.
  • Production flexibility: minimum offtake, handling of maintenance shutdowns, tenure, transfer and exit.
  • Unused energy: who carries the cost of solar the plant cannot use, and how banking, where available, is assumed.

A lower quoted tariff helps only if the delivered energy fits the plant’s operating hours. Test the proposed capacity against shutdowns and production changes before committing to a long-term offtake.

What to send for a Mandi Gobindgarh assessment

  • Factory name, location and the legal entity that holds the electricity connection
  • Furnace-wise heat schedule and auxiliaries; rolling shifts and planned outages
  • Sanctioned load, contract demand and connection voltage, exactly as on the bill
  • Twelve monthly bills and any interval (15-minute) meter data
  • Existing rooftop solar, captive generation and power contracts

BPD’s Punjab solar cluster is under development. The start of supply for any plant depends on project approvals, available allocation, connectivity and the final PPA; this guide does not describe a commissioned supply connection.

Common questions

Does a 6 MW sanctioned load mean a 6 MW solar plant?

No. Sanctioned load is one input. Useful solar capacity depends on interval demand, generation, existing solar, approved connection limits and settlement conditions.

Can solar power run an induction furnace at night?

No. A solar-only PPA supplies daytime energy and does not provide round-the-clock power or backup during a grid outage. Night-time and cloudy-hour energy still comes from the distribution licensee. Banking can shift a limited share of surplus solar, but banked energy cannot be drawn in the peak season or peak hours set by the tariff order.

What happens to solar units on a steel plant’s shutdown day?

It depends on the PPA and the regulations. A green energy open access consumer in Punjab can bank up to 30% of its monthly consumption from the licensee, on banking charges levied in kind, and unused banked energy lapses at the end of the 1 June to 31 May settlement period. The PPA should define allocation, minimum offtake and who carries the cost of unused supply.

Is 5 MW the legal minimum for open access in Punjab?

No. Above 5 MW is BPD’s current commercial priority. In Punjab, green energy open access is available to consumers with a sanctioned contract demand of 100 kVA or more, and there is no load limit for captive users.

Does BPD’s ₹4.40 offer apply to Mandi Gobindgarh steel plants?

They are BPD’s indicative offers for supply from its Punjab solar cluster, which is under development: ₹4.40 per unit ex-busbar. It is not a landed cost; the final PPA fixes the billing point, charges, losses, taxes and security.

Sources

Rules in this article are taken from the official documents below, read on 19 October 2026. Regulators amend these documents; check the version in force on your proposed supply date.

  1. PSERC (Terms and Conditions for Intra-State Open Access) (10th Amendment) Regulations, 2023, Regu. 177, 2 June 2023
  2. PSERC (Terms and Conditions for Intra-State Open Access) (11th Amendment) Regulations, 2023, Regu. 180, 12 October 2023
  3. PSERC (Terms and Conditions for Intra-State Open Access) (12th Amendment) Regulations, 2025, Regu. 195, 14 July 2025
  4. PSERC (Terms and Conditions for Intra-State Open Access) (13th Amendment) Regulations, 2026, Regu. 204, 12 May 2026
  5. Ministry of Power, Electricity (Amendment) Rules, 2026, G.S.R. 186(E), 13 March 2026: substitutes Rule 3 of the Electricity Rules, 2005
  6. PSERC, regulations currently in force (with all amendments)

This guide explains published rules in general terms. It is not legal or tax advice, and it does not describe a confirmed project, allocation or price for any factory. BPD’s indicative Punjab offers are subject to the final PPA, approvals and applicable charges.