Rooftop, open access or ground-mounted: choosing solar for a Punjab factory.

Most factories can use more than one route. The choice depends on how much daytime load you have, how much roof or land you control, how your PSPCL connection is set up, and whether you want to own the plant or buy the power.

BPD Developer · Ludhiana & ChandigarhPublished 19 October 20267 min read

Key points

  • Rooftop sits behind your meter: no wheeling charges or transmission losses on what you use, but size is limited by roof area, roof strength and the metering mode PSPCL allows for your connection.
  • Open access brings power from a larger solar plant elsewhere over the PSTCL / PSPCL network, so it can match a large load, but network charges, banking rules and, depending on the route, surcharges apply.
  • Ground-mounted plants on factory land or leased land replace the roof limit with two other questions: evacuation headroom at the nearest substation and a clean land tie-up.
  • Many factories combine routes: rooftop for part of the daytime load, open access for the balance, with each unit of load allocated to only one source.

The three routes side by side

RooftopOpen access / group captiveGround-mounted
Where the plant sitsYour shed or RCC roofA solar plant or park elsewhere in PunjabVacant land at the factory, or leased land
What limits sizeRoof area, roof strength, the metering mode allowed for your connectionEligibility, contract demand, connectivity and allocationLand and evacuation headroom at the nearest substation
Network charges on energy usedNoneTransmission and wheeling (2% in kind for renewable power within Punjab), scheduling, banking, surcharges by routeNone at the factory site; open access charges if wheeled from leased land
Main approvalsNet metering application, sanction and inspection with PSPCLGreen energy open access application, connectivity, SLDC scheduling and meteringEvacuation study, HT connectivity, land title; open access if wheeled
Ownership modelsCAPEX or RESCOThird-party PPA or group captive SPVCAPEX, RESCO or group captive SPV
Planning range≈ 8,000–10,000 sq ft of usable roof per 100 kWpCapacity allocated from a larger plant≈ 3.5–4.5 acres per MWp; 1–25 MWp; 11 / 33 / 66 kV
The question it turns onShed structureBanking terms and delivered costEvacuation headroom and land

Planning ranges are the indicative figures BPD uses for Punjab. Site-specific figures follow the structural, shadow, land and grid surveys.

Rooftop solar: when the roof can carry the load

Rooftop solar is usually the fastest route to a lower power cost when a factory has shed area and daytime load. Generation offsets consumption directly behind the meter, so there are no wheeling charges and no transmission losses on the energy you use.

Size is set by your daytime demand and the metering arrangement PSPCL allows for your connection, not by how much roof happens to be free. Grid-interactive rooftop systems in Punjab are governed by PSERC’s Grid Interactive Rooftop Solar PV Systems Regulations, 2021, which have been amended in 2024 and 2026; check the version in force for your connection’s limits.

Planning ranges we use for Punjab rooftops:

ItemPlanning range
Roof area per 100 kWp≈ 8,000–10,000 sq ft
Annual yield≈ 1,500–1,650 kWh per kWp
Typical CUF17–19%
Module warranty25–30 years performance
Worked example (arithmetic only)
50,000 sq ft of usable roof ÷ 8,000–10,000 sq ft per 100 kWp ≈ 500–625 kWp
500–625 kWp × 1,500–1,650 kWh per kWp ≈ 0.75–1.03 million units a year

Before ordering anything, the roof has to be checked: purlins, load-bearing capacity and the condition of the sheets on a metal shed, and the wind-load rating of the mounting structure on an RCC roof. A shadow analysis then sets the usable area.

Open access: when the load is bigger than the roof

Open access supplies power from a separate, larger solar plant through the PSTCL / PSPCL network, so a factory with a large sanctioned load can source far more solar energy than its roof can hold. In Punjab, green energy open access is open to consumers with a sanctioned contract demand of 100 kVA or more, and captive users have no load limit (PSERC 11th Amendment, 2023).

The price of that reach is the set of charges between the plant and your meter: transmission and wheeling, levied at 2% of energy injected for renewable power wheeled within Punjab (12th Amendment, 2025); scheduling and metering; banking terms; and, for third-party supply, cross-subsidy surcharge. Group captive avoids the surcharges when the plant meets the captive tests.

Two guides go deeper: what open access really costs and how group captive works.

Ground-mounted: when you have land

When rooftop area cannot carry the load, generation can move to land. Ground-mounted projects are won or lost on two questions asked early:

  • Grid: does the nearest substation have the headroom to take the plant’s output?
  • Land: can the land be secured cleanly, with clear title and a lease or purchase that lasts the life of the plant?

Engineering follows those answers: module technology, fixed tilt or single-axis tracker, and HT connectivity design. A plant can sit on vacant land at the factory, sized to the full daytime load rather than to roof area; on leased land elsewhere in Punjab, with power wheeled to the factory under open access or group captive; or in a shared solar park. BPD Developer’s Punjab group captive solar cluster is under development.

A simple way to decide

  1. Measure daytime load. Use twelve months of bills and any 15-minute interval data to see how much load runs between morning and evening, across seasons and holidays.
  2. Estimate what the roof can hold. Usable area divided by the planning range, then a structural check.
  3. If the roof covers most of the daytime load, rooftop is usually the first step.
  4. If there is a large gap and you have land at the factory or nearby, compare a ground-mounted plant.
  5. If the gap is large and land is not available, compare open access and group captive supply from a larger plant.
  6. Cost each route on delivered energy and compare the whole bill before and after, not tariff against tariff.

Combinations are common. A factory can put rooftop solar on its sheds and take open access for the balance. The open access allocation must then be sized after the rooftop generation is counted, so that the same load is not allocated twice.

Own the plant or buy the power

CAPEXRESCO / PPA
Upfront investmentYouDeveloper
Asset ownershipYouDeveloper
Accelerated depreciationYoursNot applicable
O&M responsibilityContractedDeveloper
Generation riskYouDeveloper
You pay forThe plantUnits consumed

Group captive sits between the two: the captive users must together hold at least 26% of the plant’s ownership under Rule 3 of the Electricity Rules, 2005, so an equity contribution is part of the structure, while the SPV builds and runs the plant.

Five common mistakes

  • Sizing by sanctioned load. Sanctioned load is a connection limit, not a measure of daytime consumption.
  • Counting the same load twice. Existing rooftop generation must be included before sizing open access.
  • Comparing tariffs instead of landed cost. A rooftop tariff and an open access tariff are not comparable until network charges, banking and surcharges are added.
  • Skipping the structural check. A shed that cannot carry the panels for the life of the plant is a more expensive problem later.
  • Carrying assumptions across states. BPD’s ₹4.40 per unit ex-busbar offer is for its Punjab cluster; plants in other states need their own state-specific assessment.

Common questions

Is rooftop solar or open access cheaper for a factory in Punjab?

It depends on the factory. Rooftop solar has no network charges on energy used, but is limited by roof area and the metering mode allowed. Open access can supply a much larger share of load, but adds network charges, banking terms and, for third-party supply, cross-subsidy surcharge. Compare the delivered cost of each against your current bill.

How much roof does a factory need for rooftop solar?

As a planning range, about 8,000–10,000 sq ft of usable roof per 100 kWp. The final layout follows a shadow analysis and a structural check of the sheds.

How much land does a ground-mounted solar plant need?

As a typical planning range, about 3.5–4.5 acres per MWp. The final figure follows the site layout and the choice of fixed-tilt or tracker structures.

Can a factory use rooftop solar and open access together?

Yes. Rooftop can cover part of the daytime load and open access the balance. Size the open access allocation after counting rooftop generation, so the same load is not allocated to both.

Can a factory get solar power without investing in a plant?

Yes. Under a RESCO or open access PPA the developer or project SPV funds the plant and the factory pays per unit consumed. Under group captive, the captive users must together hold at least 26% of the SPV’s ownership, so a small equity contribution is part of that structure.

Sources

Rules in this article are taken from the official documents below, read on 19 October 2026. Regulators amend these documents; check the version in force on your proposed supply date.

  1. PSERC (Grid Interactive Rooftop Solar Photo Voltaic Systems) Regulations, 2021, and later amendments
  2. PSERC (Terms and Conditions for Intra-State Open Access) (11th Amendment) Regulations, 2023, Regu. 180, 12 October 2023
  3. PSERC (Terms and Conditions for Intra-State Open Access) (12th Amendment) Regulations, 2025, Regu. 195, 14 July 2025
  4. Ministry of Power, Electricity (Amendment) Rules, 2026, G.S.R. 186(E), 13 March 2026: substitutes Rule 3 of the Electricity Rules, 2005
  5. PSERC, regulations currently in force (with all amendments)
  6. PSPCL, consumer procedures and commercial circulars

This guide explains published rules in general terms. It is not legal or tax advice, and it does not describe a confirmed project, allocation or price for any factory. BPD’s indicative Punjab offers are subject to the final PPA, approvals and applicable charges.